Mini hydro delivers more green energy to Victorians

02 July 2008

550Victorians will have access to more green energy thanks to a Brumby Government initiative which supports innovative small to medium-sized sustainable electricity projects.

Environment and Climate Change Minister Gavin Jennings said South East Water will generate renewable power from a mini-hydro electric generator which uses the pressure in the water mains system at Hallam.

"The project highlights the kind of practical renewable energy projects made possible by the Brumby Government's Renewable Energy Support Fund, which assists the development of innovative medium-scale renewable energy projects," Mr Jennings said.

"The Brumby Government is taking action on climate change and this 215 KW mini hydro generator will produce energy for about 160 homes in the south-east metropolitan region and will save over 1,100 tonnes of greenhouse gases per year."

South East Water has installed a mini-hydro power generator in its water supply system at an existing pressure reducing station. Energy made available through pressure reduction is now converted into renewable energy rather than wasted.

The mini generator, which has been installed between the mains and distribution pipe system, allows South East Water to solve this problem and to provide renewable power back into the grid.

It is the first time such a generator has been installed in the water network in Victoria at a pressure reducing station.

When all projects are complete, the Renewable Energy Support Fund will add more than 11 megawatts of clean generating capacity to Victoria's electricity supply. 

The projects will also collectively reduce Victorian greenhouse gas emissions by around 140,000 tonnes per year.

Green energy projects supported by the renewable energy support fund

Completed projects

 Project  Project finish date  RESF Funding  Energy Capacity  GHG Abatement (t/yr)
Kings Creek Hotel Wind Turbine  Feb-06  $30,000  95kW  120
Diamond Energy Tatura Biogas Project  Jan-07  $431,581  1.1 MW  24,500
Tullamarine Calder Solar Sound Barrier Project  Jun-07  $140,000  25kW  25
Mantra Blue Resort Warrnambool  Geothermal Heating Project  Nov-07  $235,000  330kW  550
South East Water Mini Hydro Project  Jul-08  $200,000  215 kW  1,165

Projects currently underway

Project  Project finish date  RESF Funding  Energy Capacity  GHG Abatement
(t/yr) 
Barwon Water - Montpellier Basin Mini Hydro Project  Jul-08  $160,000  184kW  550
Consolidated Energy & Resources Dandenong Green Waste to Energy Project  Dec-08  $800,000  2.4 MW  60,500
Diamond Energy Shepparton Biogas Project  Jan-09  $368,419  1.1 MW  24,500
Oceanlinx Portland Wave Energy Project  Dec-10  $1,000,000  1.5 MW  5,000
Future Energy & Hepburn Community Wind Cooperative Project  Jun-11  $975,000  4.0 MW  14,250

Projects subject to final approval

Project  Project finish date  Expected RESF Funding  Energy Capacity  GHG Abatement
(t/yr) 
Murray Goulburn Co-op Ltd Digester Gas Generation project (Leongatha)   Jun-09  $140,000  770 kW  7,500
Wallace Vegetables Solar Greenhouse Heating Project   Dec 08  $40,000  TBD  TBD

 

Media enquires